Update: Garage Foundations and Timber Frame
The foundations for the garage are complete and the Timber frame is under construction. We have completed 85% of the foundation for the house. The design for the timber frame on the house is almost complete and ready for All Timber Frames to complete from manufacturing drawings. We are looking to have the first phase of the timber frame onsite in 3 to 5 weeks.
There has been design progress to the inside of the house which has taken more time than expected (not unexpected on a project of this complexity).